The World’s First Advance Floating Gas Refinery took 7 years from concept stage to engineering completion and further 2 years for construction. This giant refinery weighs 35,000 T and 100,000 T with the carrying vessel (Blue Marlin of Dockwise BV). Refinery was constructed in Spain and presently operating for one of the gas fields in Artic Circle .

It processes the non associated gas collected through Sub Sea piping network and transports the processed gas through a Sub Sea pipeline to the onshore facility. It seems there are 5 gas turbines to run this whole refinery.